LawDistill
Supreme Court of India

M/S. MURLIDHAR CHIRANJILAL vs M/S. HARISHCHANDRA DWARKADAS AND ANOTHER on 29 March, 1961

Cites 1 provisionsCites 0 judgmentsCited by 4
Official PDFBench Pralhad Balacharya Gajendragadkar, Kailas Nath Wanchoo
PETITIONER:
M/S. MURLIDHAR CHIRANJILAL
Vs.
RESPONDENT:
M/S. HARISHCHANDRA DWARKADAS AND ANOTHER
DATE OF JUDGMENT:
29/03/1961
BENCH:
WANCHOO, K.N.
BENCH:
WANCHOO, K.N.
GAJENDRAGADKAR, P.B.
CITATION:
1962 AIR 366 1962 SCR (1) 653
ACT:
Damages-Breach of contract.-Sale of goods-Measure of
damages-Foreseeable consequence of breach-Knowledge of
parties-Indian Contract Act, 1872 (9 of 1872), s. 73.
HEADNOTE:
The appellant entered into a contract with the respondent
for the sale of certain canvas at Re. 1 per yard under which
the delivery was to be made through railway receipt for
Calcutta for Kanpur. The cost of transport from Kanpur to
Calcutta and the labour charges in that connection were to
be borne by the respondent and it was agreed that the
railway receipt would be delivered on August 5, 1947. The
appellant was unable to deliver the railway receipt on the
due date because booking from Kanpur to Calcutta was closed,
and, therefore, cancelled the contract. The respondent
instituted a suit for the recovery of damages for the breach
of the contract and claimed that as the seller knew that the
goods were to be sent to Calcutta and must therefore be
presumed to know that the goods would be sold in Calcutta,
the breach of it......
" Explanation-In estimating the loss or
damage arising from a breach of contract, the
means which existed of remedying the
inconvenience caused by the non-performance of
the contract must be taken into account."
The contention on behalf of the appellant is that the
contract was for delivery f. o. r. Kanpur and the respondent
had therefore to prove the rate of plain (not coloured)
canvas at Kanpur on or about the date of breach to be
entitled to any damages at all. The respondent admittedly
has not proved the rate of such canvas prevalent in Kanpur
on or about the date of breach and therefore it was not
entitled to any damages at all, for there is no measure for
arriving at the quantum of damages on the record in this
case. Where goods are available in the market, it is the
difference between the market price on the date of the
breach and the contract price which is the measure of
damages. The appellant therefore contends that as it is not
the case of the respondent that similar canvas was not
available in the market at Kanpur on or about the (late of
breach, it was the duty of the respondent to buy the canvas
in Kanpur and rail it for Calcutta and if it suffered any
damage because of the rise in price over the contract price
on that account it would be entitled to such damages. But
it has failed to prove the rate of similar canvas in Kanpur
on the relevant date. There is thus no way in which it can
be found that the respondent suffered any damage by the
breach of this contract.
The two principles on which damages in such cases are
calculated are well-settled. The first is that, as far as
possible, he who has proved a breach of a bargain .
to supply what he contracted to get is to be placed, as far
as money can do it, in as good a situation as if the
contract had been performed; but this principle is qualified
by a second, which imposes on a plaintiff the duty of taking
all reasonable step" to mitigate the loss consequent on the
breach, and debars him from claiming any part of the damage
which is due to his neglect to take such steps: (British
Westinghouse Electric and Manufacturing Company Limited v.
Underground Electric Railways Company of London (1)). These
two principles also follow from the law as laid down in s.
73 read with the Explanation thereof If therefore the
contract was to be performed at Kanpur it was the
respondent’s duty to buy the goods in Kanpur and rail them
to Calcutta on the date of the breach and if it suffered any
damage thereby because of the rise in price on the date of
the breach as -compared to the contract price, it would be
entitled to be reimbursed for the loss. Even if the
respondent did not actually buy them in the market at Kanpur
on the date of breach it would be entitled to damages on
proof of the rate for similar canvas prevalent in Kanpur on
the date of breach, if that rate was above the contracted
rate resulting in loss to it. Bat the respondent did not
make any attempt to prove the rate for similar canvas
prevalent in Kanpur on the date of breach. Therefore it
would obviously be not entitled to any damages at all, for
on this state of the evidence it could not be said that any
damage naturally arose in the usual course of things.
But the learned counsel for the respondent relies on that
part of s. 73 which says that dam-ages may be measured by
what the parties knew when they made the contract to be
likely to result from the breach of it. It is contended
that the contract clearly showed that the goods were to be
transported to and sold in Calcutta and therefore it was the
price in Calcutta which would have to be taken into account
in arriving at the measure of damages for the parties knew
when they made the contract that the goods were to be sold
in Calcutta. Reliance in this connection is placed on
(1) [1912] A.C. 673. 689.
two cases, the first of which is Re. R. and H. Hall Ltd.
and W. H. Pim (Junior) & Co.’s Arbitration (1). In that
case it was held that damages recoverable’ by the buyers
should not be limited merely to the difference between the
contract price and the market price on the date of breach
but should include both the buyers’ own loss of profit on
the resale and the damages for which they would be liable
for their breach of the contract of resale, because such
damages must reason ably be supposed to have been -in the
contemplation of the parties at the time the contract was
made since the contract itself expressly provided for are-
sale before delivery, and because the parties knew that it
was not unlikely that such resale would occur. ’That was a
case where the seller sold unspecified cargo of Australian
wheat at a fixed price. The contract provided that notice
of appropriation to the contract of a specific cargo in a
specific ship should be given within a specified time and
also contained express provisions as to what should be done
in various circumstances if the cargo should be resold one
or more times before delivery. That was thus a case of a
special type in which both buyers and seller knew at the
time the contract was made that there was an even chance
that the buyers could resell the cargo before delivery and
not retain it themselves.
The second case on which reliance was placed is Victoria
Laundry (Windsor) Ltd. v. Newman Industries Ltd, (2).. That
was a case of a boiler being sold to a laundry and it was
held that damages for loss of profit were recoverable if it
was apparent to the defendant as reasonable persons that the
delay in delivery was liable to lead to such loss to the
plaintiffs. These two cases exemplify that provision of s.
73 of the Contract Act, which provides that the measure of
damages in certain circumstances may be what the parties
knew when they made the contract to be likely to result from
the breach of it. But they are cases of a special type; in
one case the parties knew that goods purchased were likely
to be resold before delivery and therefore any loss by the
breach of contract eventually
(1) [1928] All E.R. 763.
(2) [1949] 1 All E.R. 997.
may include loss that may have been suffered by the buyers
because of the failure to honour the intermediate contract
of resale made by them; in the other the goods were
purchased by the party for his own business for a particular
purpose which the sellers were expected to know and if any
loss resulted from the delay in the supply the sellers would
be liable for that loss also, if they had knowledge that
such loss was likely to result.
The question is whether the present is a case like these two
cases at all. It is urged on behalf of the respondent that
the seller knew that the goods were to be sent to Calcutta;
therefore it should be presumed to know that the goods would
be sold in Calcutta and any loss of profit to the buyer
resulting from the difference between the rate in Calcutta
on the date of the breach and the contract rate would be the
measure of damages. Now there is no dispute that the buyer
had purchased canvas in this case for resale; but we cannot
infer from the mere fact that the goods were to be booked
for Calcutta that the seller knew that the goods were for
resale in Calcutta only. As a matter of fact it cannot be
denied that it was open to the buyer in this case to sell
the railway receipt as soon at it was received in Kanpnr and
there can be no inference from the mere fact that the goods
were to be sent to Calcutta that they were meant only for
sale in Calcutta. It was open to the buyer to sell them any
where it liked. Therefore this is not a case where it can
be said that the parties knew when they made the contract
that the goods were meant for sale in Calcutta alone and
thus the difference between the price in Calcutta at the
date of the breach and the contract price would be the
measure of damages as the likely result from the breach.
The contract was for delivery for Kanpur and was an ordinary
contract in which it was open to the buyer to sell the goods
where it liked.
We may in this connection refer to the
following observations in Chao and others v.
British Traders and Shippers Ltd. (1), which
are, apposite to the facts of the present
case:
(1) [1954] 1 All E.R. 779,797.
"It is true that the defendants knew that the
plaintiffs were merchants and, therefore, had
bought for resale, but every one who sells to
a merchant knows that he has bought for are-
sale, and it does not, as I understand it,
make any difference to the ordinary measure of
damages where there is a market. What is
contemplated is that the merchant buys for
are-sale, but, if the goods are not delivered
to him, he will go out into the market and buy
similar goods and honour his contract in that
way. If the market has fallen he has not
suffered any damage, if the market has risen
the measure of damages is the difference in
the market price."
In these circumstances this is not a case where it can be
said that the parties when they made the contract knew that
the likely result of breach would be that the buyer would
not be able to make profit in Calcutta. This is a simple
case of purchase of goods for resale anywhere and therefore
the measure of damages has to be calculated as they would
naturally arise in the usual course of things from such
breach. That means that the respondent had to prove the
market rate at Kanpur on the date of breach for similar
goods and that would fix the amount of damages, in case that
rate had gone above the contract rate on the (late of
breach. We are therefore of opinion that this is not a case
of the special type to which the words "which the parties
knew, when they made the contract, to be likely to result
from the breach of it" appearing in s. 73 of the Contract
Act apply. This is ,in ordinary case of contract between
traders which is covered by the words "which naturally arose
in the usual course of things from such breach" appearing in
s. 73. As the respondent had failed to prove the rate for
similar canvas in Kanpur on the date of breach it is not
entitled to any damages in the circumstances. The appeal is
therefore allowed, the decree of the High Court set aside
and of the trial court restored with costs to the appellant
throughout.
Appeal allowed

CIVIL APPELLATE JURISDICTION: Civil Appeal No.193 of 1958. Appeal by special leave from the judgment and decree dated October 3, 1955, of the High Court of Judicature, Madhya Bharat, Indore, in Civil First Appeal No. 58 of 1952. C. B. Aggarwala and Bhagwan Das Jain, for the appellant. Radhey Lal Aggarwal and A. G. Ratnaparkhi, for respondent No. 1. 1961. March 29. The Judgment of the Court was delivered by WANCHOO, J.-This is an appeal by special leave from the judgment of the High Court of Madhya Bharat. A suit was filed by firm Messrs. Harishchandra Dwarkadas (hereinafter called the respondent) against the appellant-firm Messrs. Murlidhar Chiranjilal and one Babulal. The case of the respondent was that a contract had been entered into between the appellant and the respondent through Babulal for sale of certain canvas at Re. I per yard. The delivery was to be made through railway receipt for Calcutta f. o. r. Kanpur. The cost of transport from Kanpur to Calcutta and the labour charges in that connection were to be borne by the respondent. It was also agreed that the railway receipt would be delivered on August 5, 1947. The appellant however failed to deliver the railway receipt and informed the respondent on August 8, 1947, that as booking from Kanpur to Calcutta was closed the contract had become impossible of performance; consequently the appellant cancelled the contract and returned the advance that had been received. The respondent did not accept that the contract had become impossible of performance and informed the appellant that it had committed a breach of the contract and was thus liable in damages. After further exchange of notices between the parties, the present suit was filed in November, 1947. Written statements were filed both by the appellant and Babulal. The contention of Babulal was that the contract had become incapable of performance and was therefore rightly rescinded. Further Babulal contended that he was not in any case liable to pay any damages. The appellant on the other hand denied all knowledge of the contract and did not admit that it was liable to pay any damages. Certain other pleas were raised by the appellant with which we are however not concerned in the present appeal. Three main questions arose for determination on the pleadings of the parties. The first was whether Babulal had acted as agent of the appellant in the matter of this contract; the second was whether the contract had become impossible of performance because the booking of goods from Kanpur to Calcutta was stopped; and the last was whether the respondent was entitled to damages at the rate claimed by it. The trial court held that Babulal had acted as the agent of the appellant in the matter of the contract and the appellant was therefore bound by it. It further hold that the contract had become impossible of performance. Lastly it hold that it was the respondent’s duty when the appellant had failed to perform the contract to buy the goods in Kanpur and the respondent had failed to prove the rate prevalent in Kanpur on the date of the breach (namely, August 5, 1947) and therefore was not entitled to any damages. On this view the suit was dismissed. The respondent went in appeal to the High Court and the two main questions that arose there were about the impossibility of the performance of the contract and the liability of the appellant for damages. The High Court held that the contract had not become impossible of performance as it had not been proved that the booking between Kanpur and Calcutta was closed at the relevant time. It further held that the respondent was entitled to damages on the basis of the rate prevalent in Calcutta on the date of breach and after making certain deductions decreed the suit for Rs. 16,946. Thereupon there was an application by the appellant for a certificate to appeal to this Court, which was rejected. This was followed by an application to this Court for special leave which was granted; and that is how the matter has come up before us. The same two questions which were in dispute before the High Court have been raised before us on behalf of the appellant. We think it unnecessary to decide whether the contract had become impossible of performance, as we have come to the conclusion that the appeal must succeed on the other point raised on behalf of the appellant. The necessary facts in that connection are these: The contract was to be performed by delivery of railway receipt f. o. r. Kanpur by the appellant to the respondent on August 5, 1947. This was not done and therefore there was undoubtedly a breach of the contract on that date. The question therefore that arises is whether the respondent has proved the damages which it claims to be entitled to for the breach. The respondent’s evidence on this point was that it proved the rate of coloured canvas in Calcutta on or about the date of the breach. This rate was Rs. 1-8-3 per yard and the respondent claimed that it was therefore entitled to damages at the rate of Re. 0-8-3 per yard, as the contract rate settled between the parties was R.s. 1 per yard, The quantum of damages in a case of this kind has to be determined under s. 73 of the Contract Act, No. IX of 1872. The relevant part of it is as follows:-

"When a contract has been broken, the party

who suffers by such breach is entitled to

receive, from the party who has broken the

contract, compensation for any loss or damage

caused to him thereby, which naturally arose

in the usual course of things from such

breach, or which the parties knew, when they

made the contract, to be likely to result from

the breach of it......

" Explanation-In estimating the loss or

damage arising from a breach of contract, the

means which existed of remedying the

inconvenience caused by the non-performance of

the contract must be taken into account." The contention on behalf of the appellant is that the contract was for delivery f. o. r. Kanpur and the respondent had therefore to prove the rate of plain (not coloured) canvas at Kanpur on or about the date of breach to be entitled to any damages at all. The respondent admittedly has not proved the rate of such canvas prevalent in Kanpur on or about the date of breach and therefore it was not entitled to any damages at all, for there is no measure for arriving at the quantum of damages on the record in this case. Where goods are available in the market, it is the difference between the market price on the date of the breach and the contract price which is the measure of damages. The appellant therefore contends that as it is not the case of the respondent that similar canvas was not available in the market at Kanpur on or about the (late of breach, it was the duty of the respondent to buy the canvas in Kanpur and rail it for Calcutta and if it suffered any damage because of the rise in price over the contract price on that account it would be entitled to such damages. But it has failed to prove the rate of similar canvas in Kanpur on the relevant date. There is thus no way in which it can be found that the respondent suffered any damage by the breach of this contract. The two principles on which damages in such cases are calculated are well-settled. The first is that, as far as possible, he who has proved a breach of a bargain . to supply what he contracted to get is to be placed, as far as money can do it, in as good a situation as if the contract had been performed; but this principle is qualified by a second, which imposes on a plaintiff the duty of taking all reasonable step" to mitigate the loss consequent on the breach, and debars him from claiming any part of the damage which is due to his neglect to take such steps: (British Westinghouse Electric and Manufacturing Company Limited v. Underground Electric Railways Company of London (1)). These two principles also follow from the law as laid down in s. 73 read with the Explanation thereof If therefore the contract was to be performed at Kanpur it was the respondent’s duty to buy the goods in Kanpur and rail them to Calcutta on the date of the breach and if it suffered any damage thereby because of the rise in price on the date of the breach as -compared to the contract price, it would be entitled to be reimbursed for the loss. Even if the respondent did not actually buy them in the market at Kanpur on the date of breach it would be entitled to damages on proof of the rate for similar canvas prevalent in Kanpur on the date of breach, if that rate was above the contracted rate resulting in loss to it. Bat the respondent did not make any attempt to prove the rate for similar canvas prevalent in Kanpur on the date of breach. Therefore it would obviously be not entitled to any damages at all, for on this state of the evidence it could not be said that any damage naturally arose in the usual course of things. But the learned counsel for the respondent relies on that part of s. 73 which says that dam-ages may be measured by what the parties knew when they made the contract to be likely to result from the breach of it. It is contended that the contract clearly showed that the goods were to be transported to and sold in Calcutta and therefore it was the price in Calcutta which would have to be taken into account in arriving at the measure of damages for the parties knew when they made the contract that the goods were to be sold in Calcutta. Reliance in this connection is placed on (1) [1912] A.C. 673. 689. two cases, the first of which is Re. R. and H. Hall Ltd. and W. H. Pim (Junior) & Co.’s Arbitration (1). In that case it was held that damages recoverable’ by the buyers should not be limited merely to the difference between the contract price and the market price on the date of breach but should include both the buyers’ own loss of profit on the resale and the damages for which they would be liable for their breach of the contract of resale, because such damages must reason ably be supposed to have been -in the contemplation of the parties at the time the contract was made since the contract itself expressly provided for aresale before delivery, and because the parties knew that it was not unlikely that such resale would occur. ’That was a case where the seller sold unspecified cargo of Australian wheat at a fixed price. The contract provided that notice of appropriation to the contract of a specific cargo in a specific ship should be given within a specified time and also contained express provisions as to what should be done in various circumstances if the cargo should be resold one or more times before delivery. That was thus a case of a special type in which both buyers and seller knew at the time the contract was made that there was an even chance that the buyers could resell the cargo before delivery and not retain it themselves. The second case on which reliance was placed is Victoria Laundry (Windsor) Ltd. v. Newman Industries Ltd, (2).. That was a case of a boiler being sold to a laundry and it was held that damages for loss of profit were recoverable if it was apparent to the defendant as reasonable persons that the delay in delivery was liable to lead to such loss to the plaintiffs. These two cases exemplify that provision of s. 73 of the Contract Act, which provides that the measure of damages in certain circumstances may be what the parties knew when they made the contract to be likely to result from the breach of it. But they are cases of a special type; in one case the parties knew that goods purchased were likely to be resold before delivery and therefore any loss by the breach of contract eventually (1) [1928] All E.R. 763. (2) [1949] 1 All E.R. 997. may include loss that may have been suffered by the buyers because of the failure to honour the intermediate contract of resale made by them; in the other the goods were purchased by the party for his own business for a particular purpose which the sellers were expected to know and if any loss resulted from the delay in the supply the sellers would be liable for that loss also, if they had knowledge that such loss was likely to result. The question is whether the present is a case like these two cases at all. It is urged on behalf of the respondent that the seller knew that the goods were to be sent to Calcutta; therefore it should be presumed to know that the goods would be sold in Calcutta and any loss of profit to the buyer resulting from the difference between the rate in Calcutta on the date of the breach and the contract rate would be the measure of damages. Now there is no dispute that the buyer had purchased canvas in this case for resale; but we cannot infer from the mere fact that the goods were to be booked for Calcutta that the seller knew that the goods were for resale in Calcutta only. As a matter of fact it cannot be denied that it was open to the buyer in this case to sell the railway receipt as soon at it was received in Kanpnr and there can be no inference from the mere fact that the goods were to be sent to Calcutta that they were meant only for sale in Calcutta. It was open to the buyer to sell them any where it liked. Therefore this is not a case where it can be said that the parties knew when they made the contract that the goods were meant for sale in Calcutta alone and thus the difference between the price in Calcutta at the date of the breach and the contract price would be the measure of damages as the likely result from the breach. The contract was for delivery for Kanpur and was an ordinary contract in which it was open to the buyer to sell the goods where it liked.

We may in this connection refer to the

following observations in Chao and others v.

British Traders and Shippers Ltd. (1), which

are, apposite to the facts of the present

case:

(1) [1954] 1 All E.R. 779,797.

"It is true that the defendants knew that the

plaintiffs were merchants and, therefore, had

bought for resale, but every one who sells to

a merchant knows that he has bought for are-

sale, and it does not, as I understand it,

make any difference to the ordinary measure of

damages where there is a market. What is

contemplated is that the merchant buys for

are-sale, but, if the goods are not delivered

to him, he will go out into the market and buy

similar goods and honour his contract in that

way. If the market has fallen he has not

suffered any damage, if the market has risen

the measure of damages is the difference in

the market price." In these circumstances this is not a case where it can be said that the parties when they made the contract knew that the likely result of breach would be that the buyer would not be able to make profit in Calcutta. This is a simple case of purchase of goods for resale anywhere and therefore the measure of damages has to be calculated as they would naturally arise in the usual course of things from such breach. That means that the respondent had to prove the market rate at Kanpur on the date of breach for similar goods and that would fix the amount of damages, in case that rate had gone above the contract rate on the (late of breach. We are therefore of opinion that this is not a case of the special type to which the words "which the parties knew, when they made the contract, to be likely to result from the breach of it" appearing in s. 73 of the Contract Act apply. This is ,in ordinary case of contract between traders which is covered by the words "which naturally arose in the usual course of things from such breach" appearing in s. 73. As the respondent had failed to prove the rate for similar canvas in Kanpur on the date of breach it is not entitled to any damages in the circumstances. The appeal is therefore allowed, the decree of the High Court set aside and of the trial court restored with costs to the appellant throughout. Appeal allowed