O R D E R

Leave granted.

As we thought that this matter may be given a quietus, we directed the

appellant – Board to find out some alternative plots so that the respondent may start

his business of stone crushing afresh. An allotment was made to the respondent

pursuant to the said order. As a grievance was raised that his application for grant of

electrical connection was not being proceeded with, by an order dated 15.1.2008 this

Court recorded:

“Let the matter appear in April, 2008.

In the meantime, the respondent may take possession of the

plot allotted in this favour and file an application for grant of electrical

connection within four weeks from date.

It is expected that the Power Development Department of the

State of Jammu and Kashmir shall issue necessary orders granting

electrical connection in favour of the respondent in the meantime.”

Despite the said order, no step appears to have been taken by the respondent

to take possession of the alternative plot allotted to him and apply for grant of

electrical connection. We have granted an opportunity to the learned counsel to seek

instructions from the respondent. Learned counsel for the respondent states that no

instruction has been received by her. In this view of the matter, it is not possible for us

to grant any further adjournment as it appears that the respondent is not interested in

the matter.

For the reasons aforementioned, this appeal is allowed and the impugned

judgment is set aside. No costs.