DAKSHIN HARYANA BIJLI VITRN.NIGM.LD.&ANR vs M/S EXCEL BUILDCON PVT.LTD on 25 August, 2008

Cites 0 provisionsCites 1 judgmentsCited by 0
C.A. No.-005234-005234 - 2008Official PDFBench Biswanath Agrawal, Ganpat Singh SinghviAdvocates JITENDRA MOHAN SHARMA | AMARJIT SINGH BEDI
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.5234 OF 2008
(Arising out of S.L.P. (C) No.10166 of 2007)
Dakshin Haryana Bijli Vitran Nigam Ltd.
and Another ...Appellant(s)
Versus
M/s. Excel Buildcon Pvt. Ltd. and Others ...Respondent(s)
O R D E R

Heard learned counsel for the parties.

Leave granted.

By the impugned order, the High Court of Punjab and Haryana, while

issuing notice of motion in the writ petition filed by Respondent No.1 for striking

down Clause 21-A of the Terms and Conditions of Supply framed under Section 49

read with Section 79-J of the Electricity (Supply) Act, 1948, unconditionally stayed

the demand of the arrears of electricity dues raised by the appellant-Nigam and

directed it to release electricity connection to Respondent No.1. Learned counsel for

the appellant relied upon the judgment of this Court in Dakshin Haryana Bijli Vitran

Nigam Ltd. vs. Paramount Polymers (P) Ltd. in [2006 (13) SCC 101], and argued that

the High Court was not justified in granting unconditional stay ignoring the fact that

in terms of Clause 21-A of the Terms and Conditions of Supply, Respondent No.1 was

required to pay the arrears of electricity dues amounting to Rupees eighty five lakhs

twenty one thousand and two hundred thirty five.

Learned counsel for Respondent No.1 argued that in the absence of any

stipulation in the auction notice his client cannot be burdened with the dues of

electricity payable by Respondent No.3. He submitted that the judgment relied upon

by the learned counsel for the appellant is not applicable to the present case because

validity of Clause 21-A of the Terms and Conditions of Supply which is under

challenge in the writ petition was not the subject matter of challenge in that case.

We have considered the respective arguments.

Before proceeding further, it is apposite to mention that, on 4th August,

2008, we had, after taking note of the undertaking given by the counsel for

Respondent No.1 that his client will deposit a sum of Rupees ten lakhs within two

days, directed the appellant-Nigam to restore electricity connection to the

establishment of Respondent No.1. We have been told that the aforesaid sum of

Rupees ten lakhs has been deposited and the electricity connection has been restored.

Since the writ petition filed by Respondent No.1 questioning the validity of

Clause 21-A of Terms and Conditions of Supply is pending before the High Court, it

is not proper for us to express any opinion on the merits of the case. However, we are

convinced that the impugned order is legally unsustainable. In Dakshin Haryana

Bijli Vitran Nigam Ltd. (supra), this Court interpreted Clause 21-A of the Terms and

Conditions of Supply, distinguished the earlier judgment in Isha Marbles vs. Bihar

State Electricity Board [1995 (2) S.C.C. 648] and directed the respondent to pay a

sum of Rupees twenty five lakhs with a further direction that, in the event of deposit

of the amount, the supply of electricity

will not be disconnected. In the present case, a sum of Rupees ten lakhs has already

been deposited by Respondent No.1. Therefore, we direct the said respondent to

deposit a further sum of Rupees twenty five lakhs with the Nigam. Out of this,

Rupees twelve lakhs and fifty thousand shall be deposited within three months and

the balance amount shall be deposited within three months thereafter.

Accordingly, the appeal is allowed in-part and the impugned order is

modified by directing that the stay granted by the High Court shall remain operative

if Respondent No.1 deposits Rupees twelve lakhs and fifty thousand within three

months and the remaining amount within three months thereafter. If Respondent

No.1 fails to deposit either of the instalments, the stay order passed by the High Court

shall stand automatically vacated and it will be open to the appellant-Nigam to

disconnect the supply of electricity forthwith. So far as the current electricity charges

are concerned, Respondent No.1 shall deposit the same within the time permissible

under the law and, in case it fails to do so, the Nigam would be at liberty to disconnect

the supply of electricity.

[G.S. SINGHVI] New Delhi, August 25, 2008.