Supreme Court of India

TEHRI HYDRO DEV. CORPN LTD vs JAI PRAKASH ASSO. LTD on 25 September, 2012

Cites 0 provisionsCites 3 judgmentsCited by 2
C.A. No.-003682-003682 - 2007Official PDFBench Rajendra Mal Lodha, Anil Ramesh Dave, Ranjan GogoiAdvocates SHAIL KUMAR DWIVEDI | SHARMILA UPADHYAY
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELATE JURISDICTION
CIVIL APPEAL No. 3682 OF 2007
Tehri Hydro Dev. Corpn. Ltd.& Anr. …
Appellants
Versus
Jai Prakash Asso. Ltd. …
Respondent
J U D G M E N T

This appeal is directed against the judgment and order

dated 20th July, 2006 passed by the High Court of

Uttaranchal at Nainital whereby the decree passed by the

learned trial court under the Arbitration Act, 1940

(hereinafter referred to as ‘the Act’) has been modified. The

terms of award as passed by the learned Arbitrator and the

decree passed by the learned trial court as well as the

modification thereof by the High Court will now have to be

noticed :

2.The appellants and the respondent herein had entered into a contract for execution of certain works in connection with the Tehri Hydro Dam Project. The agreement between the parties was executed on 29th March, 1978 and the works in question were completed on 31st December, 1985. The completion certificate was issued by the competent authority of the appellant-Corporation on 27th April, 1986. As the final bill of the respondent-contractor had not been JUDGMENTprepared and security money, furnished by way of bank guarantee was not released, the parties went to arbitration in accordance with the Arbitration clause under the contract/agreement. In the course of the aforesaid Arbitration proceeding the appellant-Corporation submitted a final bill which according to the respondent-Contractor entitled it to receive a sum of Rs.10,17,461.09 on account of work done besides a sum of Rs. 12..50 lakhs that was lying in deposit with the Corporation. As the amounts due. according to the respondent-contractor, had become crystallized, another arbitration proceeding between the parties for the aforesaid specific claims commenced in accordance with the arbitration clause of the agreement.

3.The award in the aforesaid arbitration proceeding was passed on 29th January, 1996 holding the respondent – contractor to be entitled to the sum of Rs. 10,17,461/- with the interest at the rate of 6% per annum from the date of invocation of the claim till the date of the award and at the JUDGMENTrate of 12% per annum from the date of the award till payment or till the award is made Rule of court, whichever is earlier. Insofar as the claim of the respondent – contractor to the sum of Rs. 12.50 lakhs lying in deposit with the Corporation, the Arbitrators held the said amount to be beyond the scope of the dispute raised in the arbitration proceeding. Accordingly, the respondent – contractor was left with the option of settling the said claim in an amicable manner or by resorting to a civil suit for recovery of the same.

4.Objections against the specific parts of the award by which the respective parties felt aggrieved were filed before the learned District Judge, Tehri, Garhwal. The learned District Judge by his order dated 15th October, 1997 upheld the claim of the respondent – contractor to the sum of Rs.10,17,461/- lakhs as awarded. In so far as the claim of Rs.12.50 lakhs is concerned, the learned trial court, notwithstanding the fact that the arbitrator did not decide JUDGMENTthe said claim, went into the issue and held the respondent – contractor to be entitled to the said amount also. Thereafter, a decree was passed in respect of the two amounts alongwith interest thereon at the rate of 12% pendente lite and 6% for the post award period. Aggrieved by the aforesaid order passed by the learned District Judge, Tehri Garhwal, the appellant moved the High Court of Uttaranchal by filing an appeal under the provisions of the Act. The High Court by its order dated 20th July, 2006 allowed the appeal in part. While the claim of Rs.10,17,461/- awarded in favour of the respondentcontractor was maintained in so far as the claim of Rs. 12.50 lakhs is concerned, the High Court took the view that the aforesaid amount could not have been awarded by the learned trial court as the said entitlement was not gone into by the learned Arbitrators. Accordingly, the High Court remanded the aforesaid claim to be settled by an Arbitrator appointed by it. Insofar as the question of interest is concerned, the High Court did not deal with the said aspect JUDGMENTof the matter at all. Aggrieved, the Corporation is before this court challenging the judgment and order dated 20th July, 2006 passed by the High Court of Uttaranchal.

5.We have heard Mr. Puneet Taneja, learned counsel for the appellants and Mr. S.B. Upadhyay, learned senior counsel for the respondent.

6.Learned counsel for the appellants has contended that the claims of the respondent - contractor for the unpaid amounts under the final bill as well as for return/refund of security deposit, including amounts furnished by way of bank guarantee, was the subject matter of an earlier arbitration between the parties. In the course of the said arbitration the final bill was placed before the arbitrators by the Corporation. On scrutiny of the aforesaid final bill the respondent-contractor claimed the two specific amounts in question and resorted to another process of arbitration JUDGMENTwithout seeking leave in the first arbitration proceeding to have recourse to a second round of arbitration. The arbitration proceeding leading to the award is, therefore, without any authority of law. Specifically, insofar as the amount of Rs.12.50 lakhs is concerned, according to the learned counsel for the appellants, the said amount was not adjudicated upon by the Arbitrators and the same was to be recovered by an amicable process or by resorting to a civil suit. In such a situation it was clearly beyond the power of the learned trial court to hold the said claim in favour of the respondent-contractor. Though the High Court was justified in setting aside the said claim of Rs.12.50 lakhs for the aforesaid reason, it could not have directed adjudication of the said issue by an Arbitrator nominated by it as has been done by the impugned order of the High Court. According to the learned counsel, the adjudication of the said claim of the respondent – contractor, if at all, should have been directed by a process contemplated by the specific provisions of the Arbitration agreement between the parties. Insofar as the grant of interest is concerned, learned counsel for the appellants has relied on Clauses 1.2.14 and 1.2.15 of Part II of the contract agreement between the parties to contend that under the aforesaid clauses of the agreement governing the parties there was a specific bar to grant of interest. Relying on several judgments of this court, details of which will be noticed in the discussions that will follow, learned counsel has contended that the award of interest in favour of the respondent-contractor being clearly contrary to the terms of the agreement between the parties is wholly untenable and therefore needs to be interfered with by this court.

7.Controverting the submissions advanced on behalf of the appellants, learned counsel for the respondent – contractor has contended that the appellants had actively participated in the proceeding before the Arbitrators and therefore, cannot, at this stage, question the jurisdiction of the Arbitrators to make the award in question. It is JUDGMENTcontended that the claim of the respondent to the amount of Rs.10,17,461/- having been held in its favour all along, the same does not disclose any basis for interference. In so far as the amount of Rs.12.50 lakhs is concerned the only issue that will require deterimination is the manner in which the de novo adjudication is required to be carried out. So far as the question of interest is concerned, learned counsel has placed before the court the UP Civil Laws (Reforms and Amendment) Act, 1976 by which certain provisions of the Arbitration Act of 1940 have been amended in its application to the State of UP. The attention of the court has been drawn to Paragraph 7A which has been added after Para 7 of the First Schedule to the Act. According to the learned counsel, Paragraph 7A authorized and empowered the arbitrator as well as the courts below to grant interest. Learned counsel has also relied on the decisions of this court in Indian oil Corporation Ltd. vs. Amritsar Gas service and others 1 , State of Orissa vs. B.N. Agarwalla 2 and Asian Techs Limited vs . Union of India and others 3 2009 10 SCC 354 JUDGMENT(para 21) in support of the contentions advanced. 1 [(1991) 1 SCC 533 2 [(1997) 2 SCC 469] 3 2009 10 SCC 354 (para 21).

8.Para 7A of the U.P. Civil Laws (Reforms and Amendment) Act, 1976 referred to above may now be reproduced : “7A. Where and in so far as an award is for the payment of money, the arbitrators of the umpire may, in the award, order interest at such rate as the arbitrators or umpire may deem reasonable to be paid on the principal sum awarded, from the date of the commencement of the arbitration as defined in sub-section (3) of section 37, to the date of award, in addition to any interest awarded on such principal sum for any period prior to such commencement, with further interest at such rate not exceeding six per cent per annum as the arbitrators or umpire may deem reasonable on such principal sum from the date of the award to the date of payment or to such earlier date as the arbitrators or umpire may think fit, but in no case beyond the date of the decree to be passed on the award.”

9.Insofar as the jurisdiction of the Arbitrator to JUDGMENT adjudicate on the two claims of Rs.10,17,461/- and Rs.12.50 lakhs are concerned, the dispute is capable of resolution within a short compass. The entitlement of the respondent – contractor to the aforesaid two amounts was not the subject matter of the earlier proceeding before the Arbitrators which arose out of the grievance of the respondent – contractor that though the execution of the work had been completed, the final bill had not been prepared and further that certain amounts lying in deposit as security had not been refunded. Once the final bill was prepared and placed before the Arbitrators the claim of the respondent-contractor got crystallized. It is these specific claims, after quantification, that had been referred to the Arbitrators in the proceeding in which the award has been passed. It will, therefore, not be correct to say that the arbitration proceeding in respect of the specific claims of the contractor stood barred in view of the earlier arbitration proceeding between the parties. That apart, from an order passed by the Arbitrators on 15th January, 1994, which is JUDGMENTavailable on record as an enclosure to the counter affidavit of the respondent, it appears that the arbitrators in the aforesaid order dated 15th January, 1994 had clearly recorded that the “. . . .both the parties agree that we should adjudicate both the disputes relating to refund of deposit of Rs.12.5 lakhs and payment of final bill to the tune of Rs.10.00 lakhs and odd . . . .” In these circumstances, the award insofar as the claim of Rs.10,17,461/- made by the learned Arbitrator and affirmed by the learned courts below will not require any further scrutiny by us.

10.Insofar as the claim in respect of the sum of Rs.12.50

lakhs is concerned, it has already been noticed that the

entitlement of the respondent – contractor to the said

amount had not been adjudicated upon by the Arbitrators on

the ground that the said issue was not an arbitrable issue

JUDGMENTand the same ought be resolved either by an amicable

process or by way of a suit for recovery. If the aforesaid

claim was not adjudicated upon by the Arbitrators the

learned trial court was patently wrong in decreeing the said

claim. Therefore, the High Court was perfectly justified in

reversing the said part of the decree. However, we do not

find any reasonable basis for the view taken by the High

Court that the entitlement of the respondent-contractor to

the said amount should now be determined by the Arbitrator

nominated by it. Rather, according to us, the aforesaid

issue should have been left for determination in accordance

with the procedure agreed upon by the parties, if the parties

are, at all, inclined to go into a further round of adjudication

at this stage. We, therefore, interfere with the aforesaid

part of the order of the High Court and, subject to our

observations above, we leave the parties to work out their

remedies as may be considered best and most appropriate

in the facts and circumstances of the case.

JUDGMENT11. This will lead the court to a consideration of what is the

principal bone of contention between the parties in the

present case, namely, the issue with regard to payment of

interest. Clauses 1.2.14 and 1.2.15 on which much

arguments have been advanced by learned counsel for both

sides may now be extracted below :

“ PART – II

The contractor agrees that no claim for

interest of damages will be entertained or

payable by the Government in respect of any

money or balances which may be lying with

Government owing to any disputes,

differences or misunderstandings between

the parties or in respect of any delay or

omission on the part of the Engineer-in-

charge in making immediate or final

payments or in any other respect

whatsoever.

CONTRACTOR :

No omission on the part of the Engineer-in-

charge to pay the amount due upon JUDGMENT measurement or otherwise shall vitiate or

make void the contract, nor shall the

contractor be entitled to interest upon any

guarantee or payments in arrears nor upon

any balance which may on the final

settlement of his accounts be due to him.”

12. A reading of the aforesaid two Clauses of the contract

agreement between the parties clearly reveal that despite

some overlapping of the circumstances contemplated by the

two Clauses, no interest is payable to the contractor for

delay in payment, either, interim or final, for the works done

or on any amount lying in deposit by way of guarantee. The

aforesaid contemplated consequence would be applicable

both to a situation where withholding of payment is on

account of some dispute or difference between the parties or

even otherwise.

13. Of the several decisions of this Court referred to by the

learned counsel for the appellant the judgments of the

Constitution Bench of this Court in Secretary, Irrigation

Department, Government of Orissa and others vs. G.C. Roy

4 JUDGMENTand anr. and Executive Engineer, Dhenkalal Minor

Irrigation Division, Orissa and others vs. N.C. Budhraj

(deceased) By lrs. And others 5 will require specific notice.

The true ratio laid down in the aforesaid two judgments

have been elaborately considered in a more recent

pronouncement of this court in the case of Union of India vs

Krafters Engineers and Leasing Private Limited 6. In Krafters

Engineers’s case (supra) the ratio of the decision in G.C.

Roy’s case (supra) was identified to mean that if the

agreement between the parties does not prohibit grant of

interest and the claim of a party to interest is referred to

the arbitrator, the arbitrator would have the power to award

the interest. This is on the basis that in such a case of

silence (where the agreement is silent) it must be

presumed that interest was an implied term of the

agreement and, therefore, whether such a claim is tenable

can be examined by the arbitrator in the reference made to

him. The aforesaid view, specifically, is with regard to

JUDGMENTpendente lite interest. In the subsequent decision of the

Constitution Bench in N.C. Budhraj’s case (supra) a

similar view has been taken with regard to interest for the

pre reference period.

14. In Krafters Engineers’ case (supra) the somewhat

discordant note struck by the decisions of this court in

Board of Trustees for the Port of Calcutta vs. Engineers-De-

Space-Age 7 and Madnani Construction Corporation Private

Limited vs. Union of India and others 8 were also taken note

of. Thereafter, it was also noticed that the decision in

Engineers-De-Space-Age’s case (supra) was considered in

Sayeed Ahmed & Co. vs. State of Uttar Pradesh & Ors. 9 and

the decision in Madnani Construction case (supra) was

considered in Sree Kamatchi Amman Constructions vs.

Divisional, Railway manager (Works), Palghat and others 10.

In Sayeed Ahmed’s case (supra) (para 24) it was held that

in the light of the decision of the Constitution bench in GC

JUDGMENTRoy’s case and NC Budhraj’s case it is doubtful whether the

observations in Engineers-de-Space-Age’s case (supra) to

the effect that the Arbitrator could award interest pendente

lite, ignoring the express bar in the contract, is good law. In

10 (2010) 8 SCC 767.

Sree Kamatchi Amman Constructions’s case(Supra) while

considering Madnani’s case (supra) this court noted that the

decision in Madnani’s case follows the decision in Engineers-

de-Space-Age’s case (supra).

15. From the above discussions, it is crystal clear that

insofar as pendente lite interest is concerned, the

observations contained in Para 43 and 44 of the judgment in

GC Roy’s case (supra) will hold the field. Though the gist of

the said principle has been noticed earlier it would still be

appropriate to set out para 44 of the judgment in G.C.

Roy’s case (supra) which is in the following terms :

“ 44. Having regard to the above

consideration, we think that the following is the JUDGMENT correct principle which should be followed in this

behalf.

Where the agreement between the parties

does not prohibit grant of interest and where a

party claims interest and that dispute (along with

the claim for principal amount or independently) is

referred to the arbitrator, he shall have the power

to award interest pendent elite. This is for the

reason that in such a case it must be presumed

that interest was an implied term of the

agreement between the parties and therefore

when the parties refer all their disputes – or refer

the dispute as to interest as such – to the

arbitrator, he shall have the power to award

interest. This does not mean that in every case

the arbitrator should necessarily award interest

pendent elite. It is a matter within his discretion

to be exercised in the light of all the facts and

circumstances of the case, keeping the ends of

justice in view.”

16. The provisions of the UP Civil (Reforms and

Amendment) Act amending the First Schedule to the

Arbitration Act, 1940 does not assist the respondent -

contractor in any manner to sustain the claim of award of

interest pendente lite, inasmuch, as paragraph 7A to the

First Schedule, as amended, is only an enabling provision

which will have no application to a situation where there is

an express bar to the entertainment or payment of interest

JUDGMENTon the delayed payment either of an amount due for the

work done or of an amount lying in deposit as security. The

decision in BN Agarwalla’s case (supra) on which reliance

has been placed by the learned counsel for the respondent,

once again, does not assist the claim of the respondent to

interest pendente lite inasmuch as in BN Agarwalla’s case

(supra) the views of the Constitution Bench in GC Roy’s case

(supra) with regard to interest pendente lite could not have

been and, infact, were not even remotely doubted. The

observation of the bench in B.N. Agarwalla’s case that in

G.C.Roy’s case (supra) the decision in Executive Eningeer

(Irrigation), Balimela and others vs . Abhaduta Jena and

others 11 was not overruled was only in the context of the

issue of award of interest for the pre reference period. The

decision in Asian Techs Limited case (supra) also relied on

by the respondent takes note of the decision in Engineers-

De-Space-Age case (supra) to come to the conclusion the

prohibition on payment of interest contained in clause 11 of

the agreement between the parties was qua the department

JUDGMENTand did not bar the Arbitrator from entertaining the claim.

It has already been noticed that the correctness of the

propositions laid down in Engineers-De-Space-Age case

(supra) have been doubted in the subsequent decisions of

this court, reference to which has already been made.

17. Clauses 1.2.14 and 1.2.15, already extracted and

analysed, imposed a clear bar on either entertainment or

payment of interest in any situation of non payment or

delayed payment of either the amounts due for work done

or lying in security deposit. On the basis of the discussions

that have preceded we, therefore, take the view that the

grant of pendente lite interest on the claim of

Rs.10,17,461/- is not justified. The award as well as the

orders of the courts below are accordingly modified to the

aforesaid extent.

18. However, the grant of interest for the post-award

JUDGMENTperiod would stand on a somewhat different footing. This

very issue has been elaborately considered by this Court in

B.N. Agarwalla (supra) in the light of the provisions of

Section 29 of the Arbitration Act, 1940. Eventually this Court

took the view that in a situation where the award passed by

the arbitrator granting interest from the date of the award

till the date of payment is not modified by the Court “.....the

effect would be as if the Court itself had granted interest

from the date of the decree till the date of payment...” In

view of the above, the grant of interest on the amount of

Rs.10,17,461/-from the date of the award till the date of the

decree or date of payment, whichever is earlier, is upheld.

In the facts of the case we are of the view that the rate of

interest should be 12% per annum as determined in the

arbitration proceeding between the parties.

19. In view of the foregoing discussions we allow this

appeal in part

and modify the order of the High Court dated 20th July,

2006 as indicated above.

[R.M.LODHA]

New Delhi, September 25, 2012.