LawDistill
Supreme Court of India

ZONAL.GEN.MANAGER,IRCON INTER.NATNL.LTD vs M/S VINAY HEAVY EQUIPMENTS on 6 May, 2015

Cites 1 provisionsCites 0 judgmentsCited by 0
C.A. No.-004211-004211 - 2015Official PDFBench Vikramajit Sen, Shiva Kirti SinghAdvocates SUDHIR KUMAR GUPTA | MUKESH K. GIRI
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4211 OF 2015
[Arising out of SLP (Civil) No. 7205 of 2007]
ZONAL GENERAL MANAGER, M/S IRCON
INTERNATIONAL LTD.APPELLANT
VERSUS
M/S VINAY HEAVY EQUIPMENTSRESPONDENT
WITH
Civil Appeal No. 4213 of 2015 [arising out of SLP (C) No. 7216 of 2007] and
Civil Appeal No. 4212 of 2015 [arising out of SLP (C) No. 33491 of 2009]
J U D G M E N T

1 Leave granted. JUDGMENT

2 The Appellant, IRCON International, is impugning the Judgment of the

Learned Division Bench of the Madras High Court, which had dismissed two

Original Second Appeals preferred by the Appellant. Recapitulating the facts of

this litigation, the Appellant was the successful tenderer in respect of a contract

awarded to it by SIPCOT (not a party to the present dispute/ Appeal), for the

construction of an Internal Road for the Industrial Complex at Irungattukottal,

Sriperumbpudur Taluk, Kanchipuram District, Tamil Nadu. The contract between

these parties was made on 10.07.1997 and was valued at Rs.13,06,60,587/-. In

furtherance of the execution of this contract, the Appellant entered into two

subcontracts (hereinafter, “the subcontracts”) with the Respondent herein, in

respect of two Packages, namely “C1” and “C2”, for the laying of roads valued at

Rs.3,20,64,752/- and Rs.1,67,01,821/- respectively. The cumulative value of both

packages amounted to Rs.4,87,66,573 /-.

3 The Respondent completed approximately 67 per cent of the work under the

two subcontracts but thereafter ceased work on both. The Appellant cancelled the

subcontracts, and managed the completion of the work by engaging other agencies.

The cost of 67 per cent of the contractual work completed by the Respondent was

estimated at Rs.3.23 crores, out of which the Appellant admittedly paid a sum of

Rs.2.62 crores. The Respondent claimed an unpaid balance of Rs.61 lakhs as arrears due to it by the Appellant,JUDGMENTand resorted to arbitration. The Appellant also took recourse to arbitration against the main contracting authority, SIPCOT, in

respect of the pending payments pertaining to C1 and C2 packages. The Arbitrator

was thus adjudicating the claims made by the Respondent against the Appellant in

the First Arbitration, and the claims made in turn by the Appellant against SIPCOT

in the Second Arbitration. The Arbitrator passed a common Award in the First

Arbitration for both packages in favour of the Respondent for the sum of

Rs.7,87,21,820/- for C1 and Rs.1,38,78,139/- for C2, both sums carrying with them

interest at the rate of twelve per cent from 04.03.2001 until the date of payment.

Interest apart, the Appellant stood liable as a result of the Award to pay the

Respondent Rs.9,25,99,959/-, including the aforementioned Rs.61 lakhs.

4 The Appellant filed two petitions (OP Nos. 107 and 108) under Section 34 of

the Arbitration and Conciliation Act, 1996, thereby separately challenging the

Award passed in respect of the two subcontracts. The Respondent filed two

applications in the two petitions, contending that while the Appellant had rejected

the Respondent’s claims of payment arrears under the two subcontracts, it had, at

the same time and contradictorily, claimed in the Second Arbitration against

SIPCOT that its dues to Respondent were in turn payable to it by SIPCOT. By a

common Order, the Single Judge dismissed the Appellant’s petitions and allowed

the Respondent’s applications. The Appellants thereafter filed two Appeals before the Division Bench of the Madras High Court, which came to be dismissed. The Appellant’s conflicting claims and statements in both arbitrations, seen and put

together, have proved determinative in the dismissal of the Appeals by the Courts

below; they shall prove similarly so here.

5 Detailing the arrears claim, it is seen that the Respondent incurred

expenditure in the execution of the subcontracts on two categories of items:

scheduled and non-scheduled. The Respondent claimed Rs.61 lakhs as its due

under both these heads. The Appellant’s principle rebuttal in resistance to the

Respondent’s claim is that the main contract (between the Appellant and SIPCOT)

and the subcontracts are wholly of a “back-to-back” nature and therefore the

liability of the Appellant would be restricted to and coextensive of that which

SIPCOT acknowledges. In other words, the acceptability and tenability of any

claim made by the Respondent against the Appellant will depend first upon that

claim’s acceptability and tenability before SIPCOT in its capacity as the employer

in the main contract. The Appellant declined to pay the Respondent for scheduled

expenditures, claiming that the Respondent had unauthorisedly performed

additional and increased quantities of works, also challenging the rate claimed by

the Respondent for the same; that the Respondent could not claim any amount in

excess of what was agreed to be paid by SIPCOT in respect of each item of work

covered under C1 and C2 subcontracts. The Appellant also rejected the Respondent’s claimed dues under the non-scheduled head (which work the Appellant itself had requested to be performed by the Respondent), stating that

SIPCOT had refuted its liability towards non-scheduled expenditures. Indeed, the

Arbitrator in his Award detected two “general pleas” as resonating from the

Appellant: firstly, that the contracts C1 and C2 were on a “back to back” basis

with IRCON’s main contract with SIPCOT and unless SIPCOT paid for the

amounts claimed by the Respondent, the Appellant was not legally liable for the

same; and secondly, that back to back basis applied even to non-scheduled items.

6 The Arbitrator found that the mention of “back-to-back” had been made only

in the contract rider agreement for Package C2, and in subsequent epistles

exchanged between IRCON and the Respondent from whose analysis two

significant factors emerge. Firstly, that “back-to-back” only meant that the terms

and conditions relating to technical specifications, and quality, quantum, manner

and method of work to be done by the Appellant in the main contract, stood

transposed on the subcontracts, C1 and C2; the primary liability of the Appellant to

the Respondent, however, stood untouched, there having been no transference or

transposition of this liability onto SIPCOT, either explicitly or implicitly.

Secondly, the Appellant had in its Written Statement before the Arbitrator,

reiterated the “back-to-back” nature and thereby agreed that the Respondent would be entitled to payment of dues as and when the Appellant received the payment for these from SIPCOT, the Respondent’s claims having been “transmitted” by the

Appellant to SIPCOT for the latter’s consideration. The Appellant has taken the

stance that it had no objection to the Arbitrator awarding a reasonable amount to

the Respondent, subject to the Appellant being awarded the same amount by the

Arbitrator in its Arbitration with SIPCOT. The Appellant was agreeable to a

direction passed against it to make payment upon realization of the sum from

SIPCOT, after a 10 per cent deduction on the sum as the Appellant’s marginal

profit. The Arbitrator, unstirred by the Appellant’s gambit at foisting the primary

liability onto SIPCOT, located primary liability as resting with the Appellant, being

the ‘employer’ in the subcontracts. The Arbitrator also instanced the Appellant’s

reprobative and approbative conduct, observing first the Appellants conditional

willingness (supra) for the passage of a favourable Award in the Respondent’s

favour, and thereafter finding a retraction of the Appellant’s position: viz. that -

“Since SIPCOT refused to pay for these claims, IRCON has taken up a new stand

that works were not done fully and payment has been made for whatever work was

done by the claimant”. Having so observed, the Arbitrator awarded as

aforementioned.

7 The Single Judge rightly upheld the Arbitrator’s repudiation of the

applicability of the “back-to-back” principle to the issue of liability of payment in the facts of this case; affirming that the Appellant as Employer was primarily liable to the Respondent. Beyond this, the Single Judge adverted to the Award obtained

by the Appellant against SIPCOT, wherein claims had been raised against SIPCOT

on the basis of the earlier Award obtained against the Appellant. The Single Judge

accepted the Respondent’s contention that “the very same claim, which the

respondent made against the petitioner has been made by the petitioner against the

SIPCOT and on that basis, an award has been passed in favour of the petitioner”.

It is facially apparent that, on the one hand, the Appellant had obtained a

favourable Award in the Arbitration with SIPCOT by substantially relying on (and

as compensation for) the adverse Award passed in its arbitration with the

Respondent; on the other hand, it appealed before the Single Judge against the

adverse Award which had substantially been the premiss and reason for the

Appellant’s success against SIPCOT. In addition, the Appellant expostulated that

the Applications before the Single Judge ought to have been heard along with the

Applications filed by SIPCOT for setting aside of the Award in Appellant’s favour

in the Second Arbitration. To not have done so would be to disjoin the Awards,

leaving it open for the High Court to come to two dissonant conclusions in the two

interdependent arbitrations; the Appellant’s expressed fear being that while its

obligation to pay, as sealed by the Award in favour of the respondent in the First

Arbitration, would be sustained, the award in its favour against SIPCOT, if heard separately, would possibly be set aside, leaving it uncompensated and liable to pay the Respondent the claimed amount. The Single Judge observed that no material

had been brought on record, nor a specific plea raised or details adduced, that

SIPCOT had filed a Section 34 petition before the same Court in a challenge

against the Award in the Respondent’s favour; a mere statement from the

Appellant’s counsel made across the bar was not sufficient materially to justify the

demand for connecting and hearing the petitions together.

8 The Learned Division Bench wholly ratified the reasoning of the Arbitrator

and Single Judge below it, finding no reason to disencumber the Appellant from

the obligation to fulfill the Respondent’s claim. While entirely agreeing with the

reasons given against the Appellant by the Arbitrator and the Courts below, we also

find additional reasons for dismissing this set of Appeals.

9 While the Award in the SIPCOT arbitration is not immediately an appellate

subject herein, yet it is still part of the record and therefore merits our

consideration. Until an order to the contrary be adduced before this Court, this

Award must be assumed to be standing and valid. Its validity and legitimacy in law,

insofar as it has depended on the earlier Award qua the adjudication of claims,

would only be justifiable by the validity of the earlier Award in the Respondent’s

favour. The earlier Award must, therefore, be presupposed to be valid, when the

validity of the later Award has not been disproved or rebutted. Seen from this dimension, the Award in JUDGMENTfavour of the Appellant is positively valid, and its unsettlement an uninviting prospect.

10 Insofar as the question of primary liability therein is concerned, the law on

subcontracts and employer liability is amply clear. In the absence of covenant in

the main contract to the contrary, the rules in relation to privity of contract will

mean that the jural relationship between the employer and the main contractor on

the one hand and between the sub-contractor and the main contractor on the other

will be quite distinct and separate. No such clause to the contrary, existent in the

main contract between Appellants and SIPCOT, has been highlighted before us by

the Appellants, which would persuade us towards a deviation from the presumption

of distinct and sole liability of the Appellant-Contractor as employer viz. a. viz. the

Respondent-Sub Contractor. On the contrary, much of the exercise in

determining the existence of a “back to back clause” in the contracts C1 and C2

appears to be misplaced. Such an accommodation or transference of liability

needs to be pinpointed in the main contract, for it is SIPCOT’s acceptance of

liability of subcontractor claims which is of the essence; even a clause indicating

“back to back” liability in agreements C1 and C2 would not serve to novate the

main contract and fasten payment liability on SIPCOT, prevented as it would be by

privity, for it would be a matter of SIPCOT’s acceptance of subcontractor liability

in the main contract, and not a matter of novation by imposition upon SIPCOT by two parties in a separate bilateral contract. Nothing presented before us suggests that SIPCOT’s contract with the Appellant provided for “back to back”

subcontracts whereby SIPCOT would be directly answerable for the payment

claims raised by contractors. That subletting was provided for by the main contract,

and indeed occurred, has been found by the Arbitrator (in both Arbitrations) and

affirmed by the Courts below. This however, is quite distinct from concluding that

SIPCOT contractually (in the main agreement) assumed primary liability for the

Subcontractor-Respondent’s payment claims in respect of agreements made with

the Appellant. The fact that the Respondent was represented and present in parleys

and meetings between SIPCOT and the Appellant or that it was referred to in the

correspondence exchanged between them does not lead to the conclusion that a

Tripartite contract had come into effect by evolution.

11 The Appellant conceded before the Arbitrator that it would countenance an

Award in favour of the Respondent as long as it was indemnified for the payment

made to the Respondent by an equal offsetting payment by way of an Award in its

favour in its arbitration with SIPCOT. The record, as has been hereinbefore

referenced, shows that the Appellant was granted precisely such an Award. The

legal import of the nature of the Appellant’s admission of liability made before the

Arbitrator in the First Arbitration now needs deliberation. The Appellant exercised

care to make this concession by conjoining therewith its demand for adjustment in the Second Arbitration. To JUDGMENTthat extent the concession could be called a conditional one. At the heart of the concession however, the admission itself, taken alone, was

not conditional. The Appellant thereby admitted an unconditional contractual

liability on its part to pay the Respondent’s contractual claim, albeit dressing the

same in the shroud of conditionality, by the expedient of making the concession

dependent upon a consequent favourable outcome in the Second Arbitration. This

was then followed by a remarkable transition in the Appellant’s legal posture, from

one of conditional agreeability, to outright denial of any and all liability on its part

to pay the Respondent, stating that SIPCOT was wholly answerable for the

satisfaction of all contractual claims and payments demanded by the Respondent,

due to the “back to back” nature of the main contract with agreements C1 and C2.

The Appellant, we find, stands bound and bonded by the legal consequences of this

initial admission made by it before the Arbitrator. Having concluded thus, we yet

underscore to observe that the Division Bench below proceeded on the merits in

this matter in upholding the Award, and did not simply hold the Appellant to

account for the consequences of its admission.

12 We also find that the Appellant’s case is not advanced by its reliance upon

the three Judge Bench decision in Oil and Natural Gas Corporation Ltd. Vs.

Western Geco International Ltd. (2014) 9 SCC 263. We cannot subscribe to the

argument on behalf of the Appellant that it was merely a Consultant and therefore could not be fastened with liability or was imperious to claims preferred by the Respondent for work contractually carried out, or, in respect of claims founded on

the bedrock of quantum meruit.

13 For the foregoing reasons, we decline to interfere with the judgment

properly exercised by the Arbitrator and Courts below, and sustain the impugned

order in its entirety.

14 Interim orders stand recalled. Appeals dismissed. Parties are to bear their

respective costs.

[SHIVA KIRTI SINGH] New Delhi, May 6, 2015.