NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No(s). 2204-2206/2012
DELHI DEVT.AUTHORITY Appellant(s)
VERSUS
PRITHI PAL SINGH & ORS. Respondent(s)
J U D G M E N T

The appellant is aggrieved by the Judgment dated 24-12-2010 of

the High Court of Delhi in Writ Petitions (Civil) Nos. 3823-3825 of

2006. By the impugned Judgment, the High Court has set aside the

Order dated 20-4-2006 whereby the request of the first respondent

for de-notification under Section 48 of the Land Acquisition Act,

1894 has been turned down. The impugned order passed by the

Government of NCT Delhi is a cryptic order mentioning only that

since the possession of the acquired land had been taken over by

the DDA on 22-2-2006, it was not possible for the D.D.A. to denotify the land under Section 48 of the Act. The High Court in the

impugned order, after examining the records, came to a finding that

there is no basis for the stand taken by the DDA that the acquired

land had already been taken into possession as per the proceedings

dated 22-2-2006 and thus observing, the matter has been remitted to

the DDA to consider the representation filed by the first

respondent afresh and to pass orders on merits. The relevant paras

of the impugned Order read as follows:-

“45. In the facts of the present case, we find that obviously

no physical possession of the land was taken over, but a

formality was completed only on the file. The representatives

of the respondents in the absence of any Halka Patwari just

went around the wall and completed a noting in the file and

this cannot be categorized as sufficient to constitute taking

over possession in view of what we have referred to aforesaid.

46. We thus come to the conclusion that no physical possession

was taken over of the site of the petitioners and it is only

when the demolition action was threatened at the site that the

petitioners approached this Court and status quo order was

passed.”

We have heard Mr. Amarendra Sharan, learned Senior counsel

appearing for the appellant – DDA, Mr. R.K. Khanna, learned Senior

counsel and other learned counsel appearing for the

respondents for quite some time.

The award is of 1979. The fist respondent had already made a

futile attempt to challenge the acquisition proceedings before the

High Court in 1978. After passing the award in 1979, it appears JUDGMENT that the first respondent made another attempt to get the award

itself declared as null and void. It is seen that the matter

remained before the Sub-Judge, Civil Court in Civil Suit No. 82 of

1979 for quite some time. The suit was ultimately dismissed on 18-

8-2005. We have referred to this factual matrix only for the

purpose of indicating the history of the litigation spanning over

to more than three decades. Taking note of the purpose for which

the land is said to be required by the appellant, taking note of

the observations made by the High Court, taking note of the

interest pursued by the Respondent Nos. 2 and 3 through the first

respondent and also taking note of the likely impact of the

subsequent legislation on land acquisition i.e. the Right to Fair

Compensation and Transparency in Land Acquisition, Rehabilitation

and Resettlement Act, 2013 (New Land Acquisition Act) (30 of 2013),

we are of the considered view that it is in the interest of all to

put a quietus, otherwise it is certainly a good case for litigation

for another couple of decades. The disputed land which has been

lying unused for last around 40 years would continue to be so while

the land is badly required if not for the housing scheme for many

other public purposes. The learned counsel appearing for the South

Delhi Municipal Corporation has also submitted on the need for some

part if not whole of the land.

Therefore, we deem it a fit case, to balance equities between

the parties and to put an end to the entire litigation, be it for

the compensation, be it for de-notification or for that matter

anything touching on road pertaining to the disputed land, and thus

for doing complete justice, to invoke Article 142 of the JUDGMENT Constitution of India.

We direct the appellant – Delhi Development Authority to limit

its claim to 3000 square meters and leave the rest to the first

respondent. This indication of 3000 sq. mtrs we have made is on the

basis of the submission that for a group housing scheme, if at all

DDA ventures for that project, the minimum requirement is of 3000

sq. mtrs. However, we make it clear while leaving the balance to

the first respondent, the appellant should also see that the first

respondent gets access to the main road and that he is in a

position to utilize the property for any of the purposes as

permitted under law. We make it clear that there shall not be any

further claim available even by way of compensation to the first

respondent or anybody claiming through him for the land in question

or for the road portion. Therefore, there is no need for

disbursement of any compensation.

The Appeals are disposed of as above. No costs.