THE ELECTRICITY DEPARTMENT, REP. BY ITS SUPERINTENDING ENGINEER, PORT BLAIR vs M/S SURYACHAKRA POWER CORPORATION LIMITED on 22 September, 2016

Cites 0 provisionsCites 0 judgmentsCited by 0
C.A. No.-001652-001652 - 2015Official PDFBench Kurian Joseph, Rohinton Fali NarimanAdvocates MOHIT PAUL
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 1652 OF 2015
THE ELECTRICITY DEPARTMENT, REP. BY ITS
SUPERINTENDING ENGINEER,PORT BLAIR AND ANR. APPELLANTS
VERSUS
M/S SURYACHAKRA POWER CORPORATION LIMITED. RESPONDENT
J U D G M E N T

1 We have heard Shri Rakesh Khanna, learned senior

counsel appearing for the appellants for quite some time,

and Shri. Gurukrishna Kumar, learned senior counsel

appearing for the respondent in reply. Though Shri Rakesh

Khanna has taken us through the PPA, various documents,

and various orders in great detail, we do not find it

necessary to go into any of these for the reason that we find that the JUDGMENTappellants had set up various expert

committees to go into the bone of contention in this

appeal, namely, project cost and completed cost.

2 We find that M/s. K.P.C.L (M/s. Karnataka Power

Corporation Ltd.) had been appointed by them in order to

determine the project cost which was determined at

Rs.73.40 crores. M/s. Tamil Nadu Electricity Generation

and Distribution Corporation Ltd. (TANGEDCO), another

expert, arrived at a finding of Rs. 82.11 crores, which

was reconfirmed by a subsequent report, and ultimately

arrived at a figure of Rs.79.439 crores with other issues

which were to be decided separately. A joint exercise

between the appellants and respondent, also carried out

in April, 2010, where a figure of Rs. 76.14 crores was

arrived at, and the balance of Rs. 8.82 crores in respect

of IDC, that is, interest during construction and

preliminary expenses was left to be examined by the

Central Electricity Authority. The Central Electricity

Authority also came out with three separate reports in

which it arrived at certain figures of project cost.

Finally, the administration appointed a five member

committee after all these reports, and in 2013, this five

member committee ultimately arrived at Rs.70.61 crores as

the final project cost. This was as follows :

“ Description of items Quantum of Para Ref. of

Expenditur Committee

e Rs. Report

Crores Approved Cost 63.14 15,17,29&30 IDC (-) 3.00 Cost excluding IDc (+) 60.14 Increase in cost of (+) 3.30 17 Establishment due to extended gestation period Increase due to Exchange (+) 5.67 Allowed as per Rate variation actual considering only 5.13 utilization

MUS$ Rs.11.0445 per dollar Additional Transformer (+) 0.31 22 and Black Start DG Set-Work done after COD Hard Cost excl. IDC 69.42 Proportionate IDC on the (+) 4.91 Revised on hard hard cost of Rs.69.11 Cr. cost Completed cost including 74.33 IDC/Project cost Liquidated damage @ 5% on (-) 3.72 Rs.74.33 crores Project Completed Cost 70.61

3 Subsequently, it has been stated that the said

report of the five member committee has been accepted by

the Administration. The Respondent had prayed that the

Hon'ble Commission determine the project cost and tariff

thereon in accordance with the provisions of PPA/Techno

Economic Clearance issued by A&N Administration and the

report of the five members committee constituted by the A

& N Administration for the purpose of determination of

the cost of the project as Rs. 70.61 crores.

JUDGMENT 4 When we pointedly referred to these reports and the

figures contained therein, together with the fact that

the respondent itself accepted the five member committee

report, which is then placed before the commission for

acceptance, we find it a little difficult to now allow

the respondent to go behind the said report. None of the

expert committee reports allow certain amounts to be

deducted from the project cost which would, if the

appellants were to succeed before us, amount to a figure

of Rs. 18.25 crores as is now argued before us by the

appellants. Even the five member committee report,

accepted by the Administration, does not include any

figures to be minused on account of under utilization of

foreign currency component of Rs. 4.149 crores;

custom-duty concession of Rs. 2.80 crores; concession in

Land Registration Charges availed by the respondent

amounting to Rs.0.3234 crores; and cost for start-up fuel

and LUBE oil for trial and test run amounting to

Rs.0.1971 crores.

5. Shri Khanna took us through the memo of appeal filed

before the Appellate Tribunal and referred specifically

to ground (C) and question of law 8(b)1 which read as

follows:

“The JERC has relied upon the reports of the

`experts' which are contrary to the PPA. JERC has

erred in giving foreign exchange variation on 7.96

MUSD. Documents submitted by the respondent

clearly show that the respondent had utilised only 9472653 DEM JUDGMENT(equivalent to 5.13 MUSD) as foreign

currency for the purpose of importing the

equipment which is mandated by the PPA.

“8(b)1. Whether the JERC has not erred by

following recommendations/reports which are in

contravention of the provisions of PPA for

computation of completed cost.”

6. We are afraid that these grounds do not help the

appellants' case. Nowhere has it been stated, in any of

the grounds that the statement made by the commission

that the five member committee report had been accepted

by the Administration is said to be incorrect. On the

contrary, the ground sought to be raised in the appeal

is that the commission has relied upon these reports,

which reports are contrary to the Power Project

Agreement. We are thus of the opinion that none of

these aspects can be looked into by us in the present

appeal. However, we find that the appellants are on

solid ground when they contend that an increase in

interest during construction, financing charges and

incidental expenses incurred for the delay in the

execution of the project due to reasons beyond the

control of the respondent has been allowed in appeal by

the Appellate Tribunal at para 23 and 36 suo moto.

7. Shri Rakesh Khanna has argued before us and shown us

the ground taken in the present appeal that the tribunal

has directed a suo moto payment of additional IDC,

financing cost and incidental expenses during JUDGMENT construction even though this was not part of the appeal

filed by the appellant M/s. Suryachakra Power

Corporation Limited before the Tribunal. This is sought

to be answered by the respondent in its counter

affidavit in this Court in paragraph (F) which reads as

under:

“In the synopsis the appellant has sought to

contend that the Tribunal has suo-moto directed

payment of additional interest during construction

(IDC), financing cost (FC) and incidental expenses

during construction (IEDC) for the period of delay

in achieving commercial operation. The appellants

have also sought to contend that the said issue

regarding additional IDC, FC and IEDC was not a

part of the appeal filed before the Tribunal. In

this context, it is respectfully submitted that the

said contention of the appellants is incorrect and

misleading. It is respectfully submitted that the

issue regarding the delay in achieving commercial

operation and to whom was the delay attributable

was pleaded and considered in detail by both the

Joint Electricity Regulatory Commission as well as

the Tribunal. Additional IDC, FC and IEDC are only

consequences that follow the delay in achieving the

commercial operation. Both the Courts below have

concurrently held that the delay in achieving

commercial operation of more than a year was

attributable to the appellants themselves as they

did not provide the transmission lines to evacuate

the power from the project within the time

prescribed under the PPA. Therefore the

Respondents herein had claimed deemed generation

charges for the whole period of delay in achieving

commercial operation. It is pertinent to mention

that the deemed generation charges is higher than

the additional IDC, FC and IEDC. Thus, the

Tribunal has granted the Respondents the lower of

the two. The deemed generation charges have been

awarded only for a period of four months out of the

total delay of more than a year in achieving

commercial operation. The Respondent is not

claiming additional IDC, FC and IEDC for the said

period of four months for which deemed generation

charges have been granted.” 8. In reply, JUDGMENTShri Gurukrishna Kumar, learned senior

counsel appearing for the respondent, points out before

us that in any case what was referred to in the

commission's judgment in order to arrive at the figure

of Rs. 78.29 crores as the project cost in fact started

with the figure of Rs. 77.595 crores, being CEA approval

as per “funds tied up” basis, which according to the

learned senior counsel, would include the aforesaid

expenditure. He argued before us that certain figures

which were referred to and relied upon by the CEA to

arrive at this figure specifically included the

aforesaid. We were not shown any such figures. We,

therefore, allow the appeal only to this limited extent

and set aside the judgment of the Appellate Tribunal

insofar as it allows an increase in interest during

construction (IDC), financing charges (FC) and

incidental expenses during construction (IEDC) incurred

for the delay in execution of the project for reasons

beyond the control of the respondent. To this limited

extent alone the appeal stands allowed, and on other

points it is dismissed.

9 We are also of the view that apart from the above,

no substantial question of law is raised in this appeal.

10 For the aforesaid reasons, we dispose of the appeal

with no other costs. JUDGMENT