M/S. GOEL GANGA DEVELOPERS INDIA PVT. LTD vs UNION OF INDIA THROUGH SECRETARY MINISTRY OF ENVIRONMENT AND FOREST on 11 September, 2019

Cites 0 provisionsCites 0 judgmentsCited by 0
2019 INSC 1018ReportableC.A. No.-010854-010854 - 2016Official PDFAuthor Deepak GuptaBench Dinesh Maheshwari
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
I.A. NO.64665 OF 2019
IN
CIVIL APPEAL NO. 10854 OF 2016
M/S. GOEL GANGA DEVELOPERS
INDIA PVT. LTD. … Applicant (s)
Versus
UNION OF INDIA THROUGH SECRETARY
MINISTRY OF ENVIRONMENT
AND FORESTS & ORS. …Respondent(s)
O R D E R

The only issue involved in this application is whether non

consideration of a judgment delivered by a three-Judge Bench in

1 (2011) 1 SCC 744

wrong conclusions by this Court with regard to the interpretation of

built up area in terms of Item No. 8 of the Schedule of the

Environment Impact Assessment (EIA) Notification dated

14.09.2006. The relevant portion of the notification reads as

follows:

8 Building/Construction projects/Area

Development projects and Townships

8(a) Building and >20000 sq. #(built up area

Construction mtrs. And for covered

projects <1,50,000 sq. construction;

mtrs. Of built- in the case of

up area# facilities open

to the sky, it

will be the

activity area)

8(b) Townships Covering an ++All projects

and Area area >50 ha under Item

Development and or built 8(b) shall be

projects up area appraised as

>1,50,000 sq. Category B1.

mtrs. ++

While interpreting this clause, one of us (Deepak Gupta, J.)

held as follows:

“13. From a bare perusal of the two hash tags (#) in

Column 4 and 5 of Item 8(a), it is apparent that what is shown

under Column 5 is actually a continuation of Column 4 and

basically it describes or defines ‘built up area’ to mean covered

construction and if the facilities are open to the sky, it will be

taken to be the activity area. This by itself clearly shows that

under the notification of 2006, all constructed area, which is

covered and not open to the sky has to be treated as ‘built up

area’. There is no exception for non-FSI area.

14. Indeed, the concept of FSI or non-FSI has no

concern or connection with grant of EC. The same may be

relevant for the purposes of building plans under municipal

laws and regulations but it has no linkage or connectivity with

the grant of EC. When EC is to be granted, the authority

which has to grant such clearance is only required to ensure

that the project does not violate environmental norms. While

projects and activities, as mentioned in the notification, may

be allowed to go on, the authority while granting permission

should ensure that the adverse impact on the environment is

kept to the minimum. Therefore, the authority granting EC

may lay down conditions which the project proponent must

comply with. While doing so, such authority is not concerned

whether the area to be constructed is FSI area or non-FSI

area. Both will have an equally deleterious effect on the

environment. Construction implies usage of a lot of materials

like sand, gravel, steel, glass, marble etc., all of which will

impact the environment. Merely because under the municipal

laws some of this construction is excluded while calculating

the FSI is no ground to exclude it while granting the EC.

Therefore, when EC is granted for a particular construction it

includes both FSI and non-FSI areas. As far as environmental

laws are concerned, all covered construction, which is not

open to the sky is to be treated as built up area in terms of the

EIA Notification dated 14.09.2006.”

The contention raised on behalf of the applicant is that since

the three-Judge Bench had in Para 84 of the judgment in the

NOIDA Park case observed that the EIA Notification dated

14.09.2006 calls for a close second look by the authorities

concerned especially in respect of the projects/activities falling

within the ambit of Items 8(a) and 8(b) of the Schedule to the

Notification which need to be described with greater precision and

clarity and the definition of built up area with facilities open to the

sky needs to be freed from its present ambiguity and vagueness, the

two-Judge Bench which delivered the judgment was bound by this

judgment of three-Judge Bench and could not have held that the

Notification dated 14.09.2006 clearly shows that all constructed

area which is covered and not open to the sky, has to be treated as

built up area.

Though the observations in Para 84, at first blush, support the

contention of the applicant, one has to appreciate the factual

background in which these observations were made. In the NOIDA

Park case, this Court was asked to intervene and halt a project in

which a huge park was being constructed. As far as Item 8(a) of the

Schedule to the EIA Notification, 2006 is concerned, the

contentions in this regard start from Para 38. The MoEF took the

stand that no environmental clearance was required because the

project area was 33.43 hectares, which was less than 50 hectares

and the built up area was 9542 sq. mtrs., which was less than

20,000 sq. mtrs.

It was contended on behalf of the petitioners and the amicus

curiae that the project would fall under Section 8(a) because though

the covered construction of the project was only 6999.50 sq. mtrs.,

the project by its very nature provided facilities open to the sky and

the whole of this open area, which was activity area, should be

treated as the built up area. The park consisted of certain

constructed structures like pathways, walkways, statues, fountains,

etc. which were open to the sky and treated as activity area. The

contention of the amicus curiae and the petitioners who were

objecting to the project was that the construction which was open

to the sky and was to be treated as activity area should also be

considered as part of the built up area.

The main dispute in the NOIDA Park case was whether the

project was a building and construction project or a township and

area development project. This Court held that this was a township

and area development project. While considering this dispute the

Court felt that there was some ambiguity. This issue did not arise

in the case in hand. The second point urged before the Court was

that the facilities open to the sky i.e. the activity area should also be

included in the built up area and it was this confusion which the

court wanted the Central Government to settle. No party had raised

any contention in the NOIDA Park case about the covered area

being built up area. All the parties were ad idem that covered

construction was built up area and the Court also held so.

This Court in this judgment has only held that all covered

construction shall be deemed to be built up area and that the

municipal laws regarding Floor Space Index (FSI) or Floor Area

Ratio (FAR) have no relevance. This issue did not arise in the

NOIDA Park case.

Therefore, in our opinion, the earlier judgment will have no

impact on the present case.

Reference was also made to Notification dated 04.04.2011 and

the Clarification dated 07.07.2017. These have already been dealt

with in the judgment dated 10.08.2018 and those were not points of

issue in the NOIDA Park case. Therefore, we find no merit in the

application and the same is dismissed accordingly.

(Deepak Gupta)

(Aniruddha Bose)

New Delhi September 11, 2019