M/S IMPERIA STRUCTURE LTD vs BRIG. HARIT PANT on 28 March, 2022

Cites 0 provisionsCites 0 judgmentsCited by 0
2022 INSC 352C.A. No.-001816 - 2022Official PDFAuthor HON'BLE THE CHIEF JUSTICEBench Shripathi Ravindra Bhat, Pamidighantam Sri Narasimha, Sarasa Venkatanarayana BhattiAdvocates VISHNU KANT
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1816 OF 2022
M/s. IMPERIA STRUCTURE LTD. Appellant
VERSUS
BRIG. HARIT PANT Respondent
O R D E R

This appeal arises out of the judgment and order

dated 11.10.2021 passed by the National Consumer Disputes

Redressal Commission, New Delhi (“the National

Commission” for short) in Consumer Case No.1043 of 2018.

The National Commission in paragraph 10 of its

judgment relied upon the decision of this Court in

Imperia Structures Ltd. v. Anil Patni & Another, (2020)

10 SCC 783. Paragraph 25 of the decision in Imperia

Structures Ltd. (supra) was as under:

“25. In terms of Section 18 of the RERA Act, if a promoter fails to complete or is unable to give possession of an apartment duly completed by the date specified in the agreement, the promoter would be liable, on demand, to return the amount received by

Mukesh Nasa wishes to withdraw from the Project. Such right of an

any other remedy available to him”. The right so given to the allottee is unqualified and if availed, the money deposited by the allottee has to be refunded

with interest at such rate as may be prescribed. The proviso to Section 18(1) contemplates a situation where the allottee does not intend to withdraw from the Project. In that case he is entitled to and must be paid interest for every month of delay till the handing over of the possession. It is up to the allottee to proceed either under Section 18(1) or under proviso to Section 18(1). The case of Himanshu Giri came under the latter category. The RERA Act thus definitely provides a remedy to an allottee who wishes to withdraw from the Project or claim return on his investment.”

Since the National Commission has followed the

decision of this Court in Imperia Structures Ltd.

(supra), we see no reason to entertain this appeal.

The Civil Appeal is, accordingly, dismissed. No

costs.

March 28, 2022.

CIVIL APPEAL NOS.1899-1906 OF 2022

M/s. IMPERIA STRUCTURE LTD. Appellant

BALJOR SINGH JAKHAR ETC. Respondents

These appeals arise out of the judgment and order

dated 11.10.2021 passed by the National Consumer Disputes

Redressal Commission, New Delhi (“the National

Commission” for short) in Consumer Case Nos.1044 of 2018,

1045 of 2018, 1046 of 2018, 1047 of 2018, 1048 of 2018,

1190 of 2018, 1191 of 2018 and 2590 of 2018.

The National Commission in paragraph 10 of its

judgment relied upon the decision of this Court in

Imperia Structures Ltd. v. Anil Patni & Another, (2020)

10 SCC 783. Paragraph 25 of the decision in Imperia

Structures Ltd. (supra) was as under:

“25. In terms of Section 18 of the RERA Act, if a promoter fails to complete or is unable to give possession of an apartment duly completed by the date specified in the agreement, the promoter would be liable, on demand, to return the amount received by him in respect of that apartment if the allottee wishes to withdraw from the Project. Such right of an allottee is specifically made “without prejudice to any other remedy available to him”. The right so given to the allottee is unqualified and if availed, the money deposited by the allottee has to be

refunded with interest at such rate as may be prescribed. The proviso to Section 18(1) contemplates a situation where the allottee does not intend to withdraw from the Project. In that case he is entitled to and must be paid interest for every month of delay till the handing over of the possession. It is up to the allottee to proceed either under Section 18(1) or under proviso to Section 18(1). The case of Himanshu Giri came under the latter category. The RERA Act thus definitely provides a remedy to an allottee who wishes to withdraw from the Project or claim return on his investment.”

Since the National Commission has followed the

decision of this Court in Imperia Structures Ltd.

(supra), we see no reason to entertain these appeals.

The Civil Appeals are, accordingly, dismissed. No

Costs.

March 28, 2022.

ITEM NO.9 COURT NO.2 SECTION XVII-A (HEARING THROUGH VIDEO CONFERENCING)

Civil Appeal No.1816/2022

M/s. IMPERIA STRUCTURE LTD. Appellant(s)

BRIG. HARIT PANT Respondent(s)

(IA No.35552/2022 – FOR EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT; and IA No.35551/2022 – FOR STAY)

Date : 28-03-2022 These appeals were called on for hearing today.

CORAM :

HON'BLE MR. JUSTICE UDAY UMESH LALIT HON'BLE MR. JUSTICE S. RAVINDRA BHAT HON'BLE MR. JUSTICE PAMIDIGHANTAM SRI NARASIMHA

For Appellant(s) Ms. Pinaki Misra, Sr. Adv.

Mr. Pravin Bahadur, Adv.

Mr. Amit Agarwal, Adv.

Ms. Kanika Gomber, Adv.

Mr. Saurabh Kumar, Adv.

Mr. S. Anjani Kumar, Adv.

Mr. Navin Kumar Sehrawat, Adv.

Mr. Vishnu Kant, AOR

For Respondent(s) Mr. Rahul Sharma, Adv.

Mr. S. Santanam Swaminadhan, Adv. Ms. Abhilasha Shrawat, Adv.

Mr. Kartik Malhotra, Adv.

Mr. Prabhash Malik, Adv.

Ms. Aarthi Rajan, Adv.

Ms. Aarthi Rajan, AOR

UPON hearing the counsel the Court made the following

The Civil Appeals are dismissed, in terms of the separate

Signed Orders placed on the file.

Pending applications, if any, also stand disposed of.